JP Piping Systems Pty Ltd undertakes larger projects for the installation of all Gas, Pneumatic and Instrumentation, Poly Lines, Fire Water, Dust Suppression, Floc Lines, Fuel Lines and any Small Bore Piping – To date we have piped out over 25 major Coal Preparation plants in Queensland’s Bowen Basin and New South Wales. Sedgman also engaged us to carryout Project Management work on the Benga Project in Mozambique.
JP Piping Systems Pty Ltd has a large range of plant and equipment and experienced staff who are specialists in managing these projects through design stage to practical completion and beyond. We are proud to say that all our projects have been completed successfully on time and on budget.
JP Piping Systems Pty Ltd has successfully completed projects up to $15.0M and has the capability and expertise to discuss any size project. We implement and maintain correct business and management practices (through our triple accreditation), together with adequate asset backing, to ensure financial stability and long-term sustainability. We are based in Mackay QLD, and supply and install all over Australia.
Projects Completed
DATE | CLIENT | PROJECT | SCOPE OF WORK |
April – August 2024 | Sedgman Pty Ltd | Mt Pleasant Mine (NSW) | Small Bore Piping |
January 2022 – August 2024 | Sojitz Blue | Gregory Mine (QLD) | Maintenance Works |
October 2021 – August 2024 | Middlemount Coal | Middlemount Mine (QLD) | Shutdown Works |
April 2018 – August 2024 | Hail Creek Coal | Hail Creek Mine (QLD) | Shutdown Works |
July 2023 – May 2024 | SCJV | Olive Downs Mine (QLD) | Supply & Install Small Bore Piping |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
August 2022 – July 2023 | Lenton Joint Venture | Bowen Coking Coal – Burton Mine (QLD) | Supply & Install Various Piping Works |
July 2022 – June 2023 | Sedgman | Olive Downs Mine (QLD) | Site Office Plumbing |
November 2022 – June 2023 | WDT | Mackay (QLD) | Supply & Install Fire Piping on Conveyors for Olive Downs Project |
November 2022 – May 2023 | Thiess | Lake Vermont Coal Project (QLD) | Fire Water Tanks |
November 2022 – Feb 2023 | Kestrel Coal | Kestrel Mine (QLD) | Supply & Install 2.5km Water Pipeline Replacement |
August 2022 – January 2023 | DRA Projects Australia | Carmichael Mine (QLD) | Install Small Bore Piping |
June 2022 – August 2022 | CMK Contracting | Marlborough (QLD) | Supply and Install Poly for Wind Farm |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
August 2021 – December 2021 | Pioneer Valley Water | Various (QLD) | Water Pump Servicing |
October 2021 – December 2021 | WDT Engineers | Mackay (QLD) | Install Fire Piping on Conveyors for Byerwen Project |
September 2021 – October 2021 | Sedgman Pty Ltd | Jellinbah Mine (QLD) | Small Bore Piping |
February 2021 – October 2021 | Wallis Group | Vanderfield Mackay (QLD) | Install new fire system |
September – 2021 | Mackay Base Hospital | Mackay (QLD) | Install plumbing for Pathology Analyser |
January 2018 – September 2021 | Sedgman Pty Ltd | Middlemount Mine (QLD) | Various small bore piping, Maintenance & Shutdown Works |
August – 2021 | BMA | Caval Ridge (QLD) | Install Hot taps |
September 2020 – July 2021 | Martinus Rail | Various sites (QLD) | Maintenance works including installing pipework and poly tanks. |
October 2020 – June 2021 | Sedgman Pty Ltd | Byerwen (QLD) | Small Bore Piping |
June 2021 – July 2021 | MJM Developments | Caval Ridge Mine (QLD) | Pipe repair – poly welding |
April 2021 – July 2021 | Eton irrigation | Victoria Plains (QLD) | Poly line installation |
April – 2021 | Pioneer Valley Water | Cattle Creek, Mackay (QLD) | Water Meter Installation |
December 2020 – January 2021 | Thiess Pty Limited | Lake Vermont (QLD) | 4.5km Poly Welding |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
September 2020 – November 2020 | BMC | South Walker Creek Mine (QLD) | Flowmeter Installation, Shutdown works. |
February 2020 – July 2020 | BHP Biliton Mitsubishi Alliance | Caval Ridge Mine (QLD) | Shutdown works, 1Mtr poly fabrication. |
December – 2019 | Farrellys Construction Services | Byerwen (QLD) | Wash plant installation works. |
August 2020 – December 2019 | G&S Engineering Pty Ltd | Gregory Mine (QLD) | Run poly pipe for Gland Water, Pipe Restoration in Thickner Tank, Installation of Poly Pipes, Fabricate new spools and install spillage pump line, Fabricate spray bar wate feeds. |
May 2019 – November 2019 | BHP Billiton Misubishi Alliance | Caval Ridge Mine (QLD) | CHPP, Raw Coal Area |
Installation, Product Stockpile Wash down, Bracket Rectification, Hydro Testing, Shutdown Works | |||
July 2019 – November 2019 | G&S Engineering Pty Ltd | Dargues Gold Mine, Braidwood (NSW) | Poly Welding, Threading Pipe, Installation of Poly and Galv Pipe, Plant Air, Gland Water, Slurry, Portable and Raw Water. |
April 2019 – November 2019 | Sedgman Pty Limited | Mt Pleasant Mine, Muswellbrook (NSW) | Installation of Small Bore Piping Systems |
February 2018 – June 2019 | G&S Engineering Pty Ltd | Caval Ridge Mine (QLD) | Piping – Stockpile Product Coal Pipe Diversion, Buried Water Line Crossings, Harrows Creek Crossing, Surge Bin Waterline |
April 2018 – February 2019 | G&S Engineering Pty Ltd | Mt Pleasant Mine, Muswellbrook (NSW) | Installation of Small Bore Piping, Dust Suppression Station, Fire Systems, Flocculant Lines, Gland Water, Air, Process Water |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
April 2018 – October 2018 | CPB Contracting | Southern Circuit, Caval Ridge (QLD) | Installation of Fire Systems, Underground Poly |
November 2016 – October 2018 | Adani | Borefield Project, Abbott Point (QLD) | Installation of 14km 180mm pipeline, Fire Line, 225mm poly, Sump discharge poly, Permanent Water, Temporary Line Stage 2 |
February 2018 – May 2018 | G&S Engineering | Caval Ridge (QLD) | Installation of Poly Screen Shrouds, Relocate Product Stockpile Sprays, Downpipe Modifications, Process Water Overflow Slab, Tie-In Fire and Gland Water, Bollards, 250mm poly line at Reclaimer, |
January – 2018 | Rio Tinto | Hail Creek (QLD) | Relocate Air Lines and Water Lines |
January – 2018 | Sedgman | Middlemount (QLD) | Supply and Install Hose Reels |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
September – 2017 | All Pumps Sales and Service | Proserpine Sewage Treatment Plant (QLD) | Installation of Fire Pumps and Pipework |
April – 2017 | SEW – Eurodrive | Paget (QLD) | Supply and Install Air System |
November 2016 – December 2016 | BMC South Walker | MRA Project, South Walker (QLD) | 40km pipe line for landowners water troughs |
November 2016 – February 2017 | BHP Daunia | Dam 4C Poly Pipe Relocation (QLD) | Supply & Relocate 355mm Poly and Pump and Mechanicals |
April – 2016 | Rio Tinto | Hail Creek (QLD) | Installation of additional Hose Down for Sizing Stations |
April 2016 – September 2016 | Downer Group | Bakers Creek & Bucasia – Sewage Treatment Plants (QLD) | Supply and Install Manifolds, Chemical lines, Injection Quill, Water Lines, Poly Tank |
March – 2016 | BMA Daunia | Daunia (QLD) | Installation of Poly Tanks |
February – 2016 | Cromford Pipe | Mackay (QLD) | Installation of Water Tanks and improvement of current Chiller Piping System. |
January – 2016 | Sedgman Millenium | Millenium (QLD) | Installation of Water Line |
November 2015 – March 2016 | BMA | Daunia (QLD) | HV Wash Rectification Works |
August 2015 – February 2016 | Mainteck | Moranbah North (QLD) | Piping Shutdown Works – CX107 |
CHPP Upgrade | |||
June 2015 – March 2016 | Tyco Australia Pty Ltd, t/a Wormald | Sino Iron Ore Mine (WA) | Installation and Commissioning Works for Fire Protection Systems |
August 2015 – November 2015 | G&S Engineering | Rolleston Coal (QLD) | Various Pipework |
November 2013 – July 2015 | G&S Engineering | Hay Point Expansion (QLD) | Fire Lines, Compressed Air Lines, Raw Water and Sewer Poly Lines, Shutdown Pipework Tie-Ins and Outloading additional pipework for Fire System, Off Shore Hydro Testing of all piping. |
March 2015 – June 2015 | Sedgman Limited | Caval Ridge Mine (QLD) | Process Water Pump Upgrade, Conduits & Pump out line, Mechanical Piping and Minor Civil Works |
November 2014 – May 2015 | Bechtel/McConnel Dowell | Hay Point Expansion (QLD) | Off shore Hydro testing of all Piping |
November 2014 – April 2015 | York Civil | Hay Point Expansion (QLD) | Final Civil Works Onshore, Welding of PE, Pipe Drainage and supply of fittings. |
July 2014 – April 2015 | Tyco Australia Pty Ltd t/a Wormald | Peak Downs Mine (QLD) | Fire System Upgrade and Civils |
September 2014 – March 2015 | Thiess Sedgman Joint Venture | Boggabri Coal Expansion (NSW) | Fire Lines, Compressed Air Lines, Process Lines, Floc Lines, Raw Water Poly Lines |
March – 2015 | Team Engineering | Grosvenor Mine (QLD) | Roof Sheeting, Wall Cladding, Ridge Vent, Gutters, Downpipes and Flashings. |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
October 2013 – September 2014 | G&S Engineering | Caval Ridge Mine (QLD) | Fire Lines, Compressed Air Lines, Process Lines, Floc Lines, Raw Water Poly Lines, Civil Works and Concreting. |
June 2014 – August 2014 | Sedgman | Goonyella Riverside Mine Spiral upgrade for CHPP (QLD) | Small Bore Services, Compressed Air Lines, Fire Lines |
March 2014 – July 2014 | BMA | Daunia Mine (QLD) | Plumbing Rectification Works, LV & HV Wash stations works |
March 2014 – August 2014 | Sedgman | Daunia Mine (QLD) | Floc System Upgrade, MIBC Flowmeter Install |
September 2013 – January 2014 | Thiess | Caval Ridge Mine CHPP (QLD) | Fire Lines, Compressed air Lines, Process Lines, Floc Lines, Raw Water Poly Lines |
October 2103 – March 2014 | Thiess | Caval Ridge Mine MIA (QLD) | Heavy Vehicle and Light Vehicle Wash Bay & Fuel Lines |
November 2013 – December 2013 | Sedgman | Mungari Gold (WA) | Project Management – Piping |
February 2013 – April 2013 | Sedgman | Saraji Mine, Reflux Classifier Project (QLD) | Site Offices Plumbing, Fluidising Water, Small Bore Process Piping, Instrument & Service Air, Wash Down System, Fire System |
January 2013 – March 2013 | York Civil | Daunia Mine (QLD) | Poly Welding – 450mm lines |
January 2013 – April 2013 | Downer EDI | Daunia Mine (QLD) | Plumbing & Drainage, Administration Buildings & Workshop |
February 2013 – November 2013 | Thiess | Daunia Mine (QLD) | Heavy Vehicle and Light Vehicle Wash Bay & Fuel Lines |
September 2012 – December 2012 | Team Engineering Services | Clermont Coal Dump Hopper Upgrade (QLD) | Fire Lines, Dust Suppression, Raw Water Lines. |
July 2102 – December 2013 | Downer/Bechtel | Sth Walker Mine Flotation Cell Project (QLD) | Fire Lines, Compressed air Lines, Process Lines, Floc Lines, Raw Water Poly Lines |
February 2011 – June 2012 | BMC | Sth Walker Mine (QLD) | Up Grade all Piping in CHPP |
January 2011 – 2013 | Anglo Coal | Moranbah Nth CHPP (QLD) | Up Grade Fire and air Systems in CHPP and Conveyors, Fire System Audit |
March – 2012 | Goldings | Daunia Mine (QLD) | 3.5km 250mm Dewatering Poly Lines |
January 2011 – 2013 | Anglo Coal | Moranbah Nth CHPP (QLD) | Up Grade Fire and air Systems in CHPP and Conveyors, Fire System Audit |
February 2011 – June 2012 | BMC | South Walker Mine (QLD) | Up Grade all Piping in CHPP |
October 2011 – March 2012 | Thiess Sedgman Joint Venture | Bengalla CHPP Expansion (NSW) | Install Floc Lines , Fire Lines, Process Lines and Compressed air lines |
July 2011 – October 2011 | Sedgman | Benga Project Mozambique | Project Management – Piping |
January 2011- October 2011 | Sedgman | Narrabri Coal Mine (NSW) | Install Floc Lines , Fire Lines, Process Lines and Compressed air lines |
January 2010 – 2013 | Roche Downer EDI Mining | Millennium Mine (QLD) | Plumbing, Supply of Poly Pipe and Installation |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
September 2009 – November 2009 | WALZ | Carborough Downs CHPP Project (QLD) | Install Airlines & Piping |
July 2009 – December 2009 | Sedgman | Coppabella Tailings Dam (QLD) | Install Pumps, Poly Lines, Drainage |
2009 | Xstrata Zinc | Mt Isa Mines (QLD) | Supply contract for Poly Pipe and Fittings |
June 2009 – September 2009 | Sedgman | Sonoma Mine Micro Cell Upgrade (QLD) | Fire lines, Airlines, Diesel lines, Process Water Lines, Roofing, Floc Lines etc. |
April 2009 -July 2009 | Sedgman | Bengalla Mine Upgrade (NSW) | Install Fire lines, Dust Suppression , Roofing and Poly lines |
2008 | Sedgman | Blair Athol (QLD) | Supply& Install Fabricated Poly Pipe Items for CHPP |
2008 | Hamilton Island | Dent Island Golf Course Project (QLD) | Supply approx.’ 500K of Poly Pipe, Valves and E/F Fittings |
2008 | Sedgman | Millennium Mine (QLD) | Shutdown works, Poly lines, Fire Lines etc |
2008 | Sedgman | Coppabella Mine (QLD) | Ongoing shutdown works, Co-disposal lines and Poly lines in CHPP |
April 2008 – June 2008 | Thiess Sedgman Joint Venture | Lake Vermont (QLD) | Install Fire Services off site for Conveyor Galleries. |
June 2008 – September 2008 | Sedgman | Coppabella Mine (QLD) | Upgrade Fire Service in Tunnel |
January 2008 – June 2008 | Sedgman | Middlemount Coal (QLD) | Site Set up of Offices, Air, Water, Fire Water, Poly Mains. |
October 2007 – November 2007 | SKM | Solomon Islands | Installation of 8km 160mm, 125mm Poly Water Main and Pump Stations |
November 2007 – March 2008 | Metals Finance Corporation | Lucky Strike Nickel Project | 30km Poly Pipe line from Burdekin River to new mine site |
July 2007- Current | Sedgman | Millennium Coal (QLD) | Providing CHPP Plant Operators |
July 2007 – June 2008 | Thiess Sedgman Joint Venture | Lake Lindsay Coal Mine (QLD) | Installation of Poly Compressed Airlines, Fire Water, Floc lines, Roofing and Wall Cladding of CHPP and Train Load Out. |
July 2007 – January 2008 | Team Engineering Services | Dalrymple Coal Terminal Stacker a d Reclaimer Upgarde (QLD) | Re pipe Stacker Reclaimer in S/S Pipe for, Fire Water and Dust Suppression. |
July 2007- January 2008 | Sedgman | Sonoma Mine (QLD) | Installation of Compressed Air lines, S/S Fire water. Poly Waterlines, Roofing and Poly Drains. |
Site set up of all Offices, Sewer Plant and Crib Rooms | |||
March 2007- 2010 | Sedgman | Coppabella CHPP Piping upgrade (QLD) | Replace Air, Water lines with Poly. S/S and Victaulic. |
February 2007- December 2007 | Thiess Sedgman Joint Venture | Dawson Alliance CHPP (QLD) | Compressed Air lines, Fire Water, Dust Suppression, Floc Lines, Poly Fire Lines, Sewer Lines, Coolfit lines, Raw Water lines, Washdown lines, Poly Drains. |
November 2006- January 2007 | Sedgman | Acland CHPP (QLD) | Compressed Poly Air lines, Floc lines, Fire Lines |
March 2006 – October 2006 | Excel Coal | Millennium Mine CHPP (QLD) | Compressed Air, Dust Suppression, Small Bore Piping and Fire Services |
November 2005 – April 2006 | Thiess Sedgman Joint Venture | Saraji CHPP Expansion (QLD) | Compressed Air and Fire Water Poly Lines |
January 2006 – June 2006 | O’Donnell Griffin | Water Reticulation Hail Creek Expansion (QLD) | Poly Lines, Pontoons, Dams and Pump work |
June 2005 – September 2006 | Thiess Sedgman Joint Venture | Hail Creek Expansion (QLD) | CHPP, Administration Building and Workshops |
March 2005 – September 2005 | Parrotta Engineers | BE Project – Workshop Facilities and Administration Building (QLD) | Sewerage, Storm Water, Fire Water and Plumbing |
September 2004 – January 2005 | Sedgman | Curragh CHPP Upgrade (QLD) | Compressed Air lines and Poly lines. |
July – 2004 | Sedgman | De-Watering Plant Dartbrook Coal Mine Hunter Valley (NSW) | Compressed air, Potable Water Lines. |
December 2003—January 2004 | Thomas Borthwicks & Sons Meat works | Christmas shutdown (QLD) | Re-design and install Sterilizer Poly Drainage System . |
December – 2003 | HF Hands | Gregory Mine. (QLD) | Roofing and Wall cladding. |
Wash plant expansion | |||
August – 2003 | Parrotta Engineering | Moorvale Coal Project (QLD) | Re-location of Leighton’s work shop |
August 2003—November 2003 | Sedgman | Moorvale Coal Project (QLD) | Fire Lines, Compressed air Lines, Process Lines, Floc Lines, Raw Water Poly Lines |
March 2003—September 2003 | Thiess Sedgman Joint Venture | Hail Creek Coal Project (QLD) | Fire Lines, Compressed air Lines, Process Lines, Floc Lines and Raw Water. Roofing and cladding, Water installation, Fire service installation. |
December 2002— March 2003 | Parrotta Engineering | CCME Workshop and Offices expansion. (QLD) | Roofing, Wall Cladding, Sewerage, Hot and Cold Water. |
November 2002—February 2003 | Parrotta Engineering | Coppabella Coal Mine. (QLD) | Drainage, Compressed Air, |
Work shop expansion. | Fire services, Roofing and Wall Cladding, Lube lines. | ||
November 2002—January 2003 | Thomas Borthwicks & Sons | Construction and Relocation of New Knocking Box (QLD) | Compressed Air lines, Flow Return Water, Sterilizer water, Drainage, Stainless Steel installation. |
September – 2002 | Thiess Sedgman Joint Venture | Site Establishment for Hail Creek Coal Project. (QLD) | Water, Pressurized Sewer Main connections to site offices. |
May 2002 — Aug 2002 | Thomas Borthwicks and Sons Meat Works. | General Maintenance (QLD) | Water Reticulation, Cooling Towers, Compressed Air Installation, Roofing and Cladding. |
February 2002 — March 2002 | Sedgman | Wash plant expansion | Installation of all Pneumatic Piping and Instrumentation. |
Coppabella Coal Mine (QLD) | |||
November 2001 – December 2001 | Barclay Mowlem | Stage 5 DBCT Expansion | All Stainless Steel Water Supplies for Dust Suppression and Fire Water. |
PCQ. (QLD) | 160mm Electrofusion Poly Water lines. | ||
Pneumatics for Rail Receival. | |||
March 2001 – June 2001 | O’Donnell Griffin/ | Oaky Creek Coal Mine (QLD) | All Pneumatics and Compressed Air supply to Instruments. |
Sedgman | New Wash Plant | Drainage for Wash Plant and Tunnels. | |
June 2000– September 2000 | Thomas Borthwicks & Sons Meat works | Separation of sterilizing water. | 100mm Giberit HDPE Drainage Systems. |
Construction of new Meat Meal load out facility. | 50mm gal’ pipe work. | ||
Roofing & Cladding. | |||
November 1999 – March 2000 | Lacaba Ahden | BHP Peak Downs Mine (QLD) | All External & Internal Sheeting. |
B.E. Dragline | Wall Cladding of B.E. Dragline |
DATE | CLIENT | PROJECT | SCOPE OF WORK |
November 1999 – December 1999 | Pacific Hydraulics | BHP Hay Point (QLD) | 25mm – 50mm Gal Compressed Air and Pneumatics |
Kwik Drop System | |||
Rail Receival | |||
November 1999 – December 1999 | Team Engineering Services | Dalrymple Bay Coal Terminal Shutdown SR4 / SR5 (QLD) | Additional Water Dust Suppression and Belt Sprays |
June 1999 – November 1999 | Transfield | Mackay Raw Sugar | Installation of Air and Water.25mm-65mm Gal Pipe for galleries. Installation of Air and Water for Ship loader. |
Wharf Project (QLD) | Drainage for transfer towers. | ||
February – 1999 | Fraser Engineers | I.P.S. (QLD) | Installation of 650mm Duct for Exhaust Fans |
November – 1998 | Pacific Hydraulics | BHP Hay Point | 25mm – 50mm Gal Compressed Air and Pneumatics |
Kwik Drop System | |||
Rail Receival (QLD) | |||
June – 1998 | Pacific Hydraulics | Dalrymple Bay Coal Terminal (QLD) | 25mm – 50mm Gal Compressed Air and Pneumatics |
Kwik Drop System | |||
Rail Receival | |||
March – 1998 | Pacific Hydraulics | Dalrymple Bay Coal Terminal (QLD) | 25mm – 50mm Gal Compressed Air and Pneumatics |
Kwik Drop System | |||
Rail Receival | |||
January 1998 – July 1999 | Lacaba Ahden | Dalrymple Bay Coal Terminal (QLD) | 65mm Gal Water supply for Fire systems and Dust Suppression. |
Stacker/Reclaimer SR4 and SR5 | 25mm Compressed Air and Pneumatics. | ||
June 1997 – January 1998 | Lacaba Ahden | BHP Cannington (QLD) | 25mm – 50mm Gal Pipework for Water, Fire Systems, Sprays and Pneumatics. |
Ship Loader | 80mm PVC Vacuum System. |